Progress Update 7/11/17

2328: Unit 1: The electrician has begun trimming out this unit. Plumbing trim is complete except for sinks (waiting on countertops which should be set this week). Unit 2: Electrican’s crews are working in this unit as well. Plumbing trim in progress, but will be incomplete until countertops arrive. This unit’s countertops were part [...]

By | July 11th, 2017|Uncategorized|0 Comments

Progress Update 6/28/17

Overall Site Progress: Landscaping has begun on the rear portion of the lot, with soil, irrigation, and plants all installed. River rock installation is expected to begin this week. Building 2328: Unit 1 & 2: Cabinets are installed and tile is complete in both of these units. Unit 3 & 4: Hardwood is acclimating on [...]

By | June 28th, 2017|Uncategorized|0 Comments

5/16/17

Exterior painting on buildings 2328 and 2330 is almost complete. The GC has sent out a first round of punch lists to all subs for the first two units (units #3 and #4) in 2328, and the remaining units should stagger a week or two behind. In building 2328, insulation is installed through unit [...]

By | May 16th, 2017|Uncategorized|0 Comments

4/18/17 Progress Update

In building 2328 unit #2, Batt insulation is 90% complete. Insulation is stocked and ready to install in unit #1. In building 2330, paint is complete in units #4 and #3. Plumbers will be starting trim tomorrow. Unit #2 - cabinets are stocked. Tile and hardwood are also complete.     [...]

By | April 18th, 2017|Uncategorized|0 Comments

1/23 Construction Update

Building 2326 & 2332  Xcel has finally installed gas meters as of 01/19. The general contractor immediately reached out to the subcontractors for all remaining work and is in the process of confirming new schedules with all of them. The general contractor has committed to issuing a new master construction schedule by the middle [...]

By | January 23rd, 2017|Uncategorized|0 Comments

12/9 Construction Progress

Xcel is almost complete with all the infrastructure upgrades necessary. Building 2330 Multiple units have now been inspected and draft stop and installation is underway and we should be seeing drywall be stocked and hung in the upcoming weeks. Building 2328 Framers are on site and are working through the first floor. [...]

By | December 9th, 2016|Uncategorized|0 Comments