Construction Progress

Progress Update 7/11/17

2328: Unit 1: The electrician has begun trimming out this unit. Plumbing trim is complete except for sinks (waiting on countertops which should be set this week). Unit 2: Electrican’s crews are working in [...]

July 11th, 2017|

Progress Update 6/28/17

Overall Site Progress: Landscaping has begun on the rear portion of the lot, with soil, irrigation, and plants all installed. River rock installation is expected to begin this week. Building 2328: Unit 1 & 2: [...]

June 28th, 2017|

5/16/17

Exterior painting on buildings 2328 and 2330 is almost complete. The GC has sent out a first round of punch lists to all subs for the first two units (units #3 and #4) in [...]

May 16th, 2017|

4/18/17 Progress Update

In building 2328 unit #2, Batt insulation is 90% complete. Insulation is stocked and ready to install in unit #1. In building 2330, paint is complete in units #4 and #3. Plumbers will be [...]

April 18th, 2017|

1/23 Construction Update

Building 2326 & 2332  Xcel has finally installed gas meters as of 01/19. The general contractor immediately reached out to the subcontractors for all remaining work and is in the process of confirming new [...]

January 23rd, 2017|

12/9 Construction Progress

Xcel is almost complete with all the infrastructure upgrades necessary. Building 2330 Multiple units have now been inspected and draft stop and installation is underway and we should be seeing drywall be stocked and hung [...]

December 9th, 2016|